July 2008
Were TOPPED OFF!
The final residential floor at level 47 and the beacon up to level 48
Block level 40,
Glass level 40,
Stucco on level 38,
Exterior paint level 37
Balcony rails level 32
Layout level 39,
Sprinkler rough level 37,
Ductwork level 37,
Standing studs level 36,
Electrical rough level 35,
Tubs and shower pans level 35,
Gypsum wall board level 31,
Tape and finish level 29,
Wood doors level 24,
Tile and marble level 22
Kitchen cabinets level 21,
Shower doors level 18
Vanities level 17,
Barnyard doors level 12
Plumbing fixtures level 9
Lobby – Frame north sitting walls and mail room, electric feeders run at ceil to commercial “A” .
Fire command center wire pull on going, elevator remote enunciator and controller mounted
Penthouse terraces waterproofing and topping slab continues to level 39
Leave out bay poured level 3 partial.
|