July 2008

Were TOPPED OFF!

The final residential floor at level 47 and the beacon up to level 48

  • Block level 40,
  • Glass level 40,
  • Stucco on level 38,
  • Exterior paint level 37
  • Balcony rails level 32
  • Layout level 39,
  • Sprinkler rough level 37,
  • Ductwork level 37,
  • Standing studs level 36,
  • Electrical rough level 35,
  • Tubs and shower pans level 35,
  • Gypsum wall board level 31,
  • Tape and finish level 29,
  • Wood doors level 24,
  • Tile and marble level 22
  • Kitchen cabinets level 21,
  • Shower doors level 18
  • Vanities level 17,
  • Barnyard doors level 12
  • Plumbing fixtures level 9

  • Lobby – Frame north sitting walls and mail room, electric feeders run at ceil to commercial “A” .
    Fire command center wire pull on going, elevator remote enunciator and controller mounted

  • Penthouse terraces waterproofing and topping slab continues to level 39

  • Leave out bay poured level 3 partial.
  •  
    CONSTRUCTION
    1 2 3 4 5 6 7
    PARAMOUNTBAY

    HOME
    CONTACT

    Paramount Bay Site: 2066 N. Bayshore Drive, Miami, FL 33137
    Sales Center: 700 N.E. 2nd Avenue, Miami, FL 33132

    Sitemap
    Powered by Turbonacho